Friday, October 29, 2004

its almost theater

What we did:
  • The escape stairs are up.
  • The escape railings are drawn and in-process.
  • The door groove was omitted. We need to fix this on monday, before it gets painted. No big deal... shannon caught it from the design drawings, I'll have Avery do it before crew.
  • The second railing pieces were cut.
  • All of the aluminum was cleaned per Ben Carter's direction.
  • The Cut Black Drop is cut. And very neatly folded like a drop, in a box and stored in PTM, far, far away from the forces of evil that might damage it.
  • The Gauze Hanger is fully pre-rigged (tie lines attached in the grommets) and stored in StuTech, under my desk, in a bag
  • The lower stairs are assembled as stairs. We need more 3/8 MDF

Monday's plan:

  • 9am: order more materials with Kevin's card.
  • 1pm: Tech Design
  • 1:30 pm: Avery starts work on finishing the lower stairs
  • 5:30 pm: Avery goes on Dinner Break
  • 6:30 pm: Crew and Avery start work
  • Avery works on jigging up the second railing
  • Shannon +2 pre-rig Wall C
  • Michelle +1 works on Facing
  • Sarah +1 works on Kick blocks
  • Escape railing is in a holding pattern

The Weekend Plan:

  • Sleep in tomorrow.
  • Finish all drawing and tech design for the show.
  • Have a "materials to order" list ready for Monday morning.
  • Go to the Evaline party Saturday night.
  • Eat lunch at Uncle Sam's on Sunday
  • Do laundry
  • Do some homework for Kevin's classes.

Yay! for being done with this before midnight.

Love, Katy